Next steps & schedule

[step 5 of 6]

Next steps & schedule

On June 13, 2017, SRP filed an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC) for a new 4.8-mile line from the Knox substation to a new RS-27 substation.

Final CEC approval

The Arizona Power Plant and Line Siting Committee held public hearings July 24–25 and recommended approval of the CEC application. The ACC granted approval of a CEC for the project on Sept. 12. The approval, by unanimous vote, is the final step of the application process and enables SRP to move forward with project construction.

For more information about the Certificate of Environmental Compatibility process, please visit the Arizona Corporation Commission (ACC) website.

Past events and hearings

Date/Time Details Location

Sept. 12, 2017
10 a.m.

Arizona Corporation Commission open meeting

Hearing Room One
1200 W. Washington St.
Phoenix, AZ 85007

July 25, 2017

CEC Line Siting Committee hearing

and route tour

Crowne Plaza Phoenix Chandler Resort
1 N. San Marcos Place
Chandler, AZ 85225

July 24, 2017
6 p.m.

CEC public comment evening session

Crowne Plaza Phoenix Chandler Resort
1 N. San Marcos Place
Chandler, AZ 85225

July 24, 2017
10 a.m.

CEC Line Siting Committee hearing

Crowne Plaza Phoenix Chandler Resort
1 N. San Marcos Place
Chandler, AZ 85225

June 1, 2017
4–8 p.m.

Open house

Crowne Plaza Phoenix Chandler Resort
1 N. San Marcos Place
Chandler, AZ 85225

April 25, 2017
5–8 p.m.

Open house

Hilton Phoenix Chandler
2929 W. Frye Road
Chandler, AZ 85224