On June 13, 2017, SRP filed an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC) for a new 4.8-mile line from the Knox substation to a new RS-27 substation.
Final CEC approval
The Arizona Power Plant and Line Siting Committee held public hearings July 24–25 and recommended approval of the CEC application. The ACC granted approval of a CEC for the project on Sept. 12. The approval, by unanimous vote, is the final step of the application process and enables SRP to move forward with project construction.
For more information about the Certificate of Environmental Compatibility process, please visit the Arizona Corporation Commission (ACC) website.
Past events and hearings
Date/Time | Details | Location |
---|---|---|
Sept. 12, 2017 |
Arizona Corporation Commission open meeting |
Hearing Room One |
July 25, 2017 |
CEC Line Siting Committee hearing and route tour |
Crowne Plaza Phoenix Chandler Resort |
July 24, 2017 |
CEC public comment evening session |
Crowne Plaza Phoenix Chandler Resort |
July 24, 2017 |
CEC Line Siting Committee hearing |
Crowne Plaza Phoenix Chandler Resort |
June 1, 2017 |
Open house |
Crowne Plaza Phoenix Chandler Resort |
April 25, 2017 |
Open house |
Hilton Phoenix Chandler |